Project schedule

Longonot Geothermal Project
Agil completed the preparation phase of the project in July 2010 and is now preparing for second phase, which is exploration.

Construction activities for exploration drilling are expected to start in late 2013.  After the appraisal and construction phases, commercial operation is currently scheduled to begin with the commissioning of the plant in 2018.

In a project of this size, and at this early stage, there are many factors that may cause delays to the proposed timeline, or enable it to be completed faster.  Agil commits to communicate any changes to the timeline as soon as practicable.